Duke: Cleanup At Dan River Plant Will Take 2 Years

RALEIGH, N.C. (AP) -- Duke Energy says it plans to move three leaky coal ash pits away from North Carolina waterways, including one that coated 70 miles of the Dan River with toxic sludge.


Duke says it will take at least two years to clean up the Dan River site, and sites near Asheville and Charlotte. State regulators say Duke's plans fall short of cleaning up nearly three dozen leaky coal ash dumps spread across the state.


After the Feb. 2 spill, Gov. Pat McCrory and regulators gave Duke a March 15 deadline to provide details of how the company would stop pollution at the ash pits.


Duke President Lynn Good sent Department of Environment and Natural Resources Secretary John Skvarla a letter with details.


But on Thursday, Skvarla called the plans inadequate.


InfoCenter


RDU Radar


Triangle Traffic

Reports | Cams

Air Quality

Pollen Forecast

Station Events

 



Advertisement:

On Air Now

Dr. Joy Browne

Dr. Joy Browne

9:00pm - 12:00am
Call: 1-800-544-7070

Next Up:

Dr. Joy Browne

On Air Now

Hall Of Fame Music

Hall Of Fame Music

7:00am - 12:00am

Advertisements

Listener Club Login

Club Login
Sign up if you are not already a member